e-able

Proof

A Hong Kong data centre, measured.

GRANDER Circulation Revitalisation Devices on the cooling and chilled-water circuits of a Hong Kong data centre. Before and after, on the site's own meters.

This page shows exactly how we measured, what we adjusted for and where the figures are limited. Engineers and finance teams can check every step.

Preliminary, site-specific results.

Estimated savings a yearHK$399,134.50Estimated from the measured energy and water savings.
14%About 14% less cooling energy (61,288 kWh), weather-adjusted
28%About 28% less water (1,864 m³)
4.8 yrsPayback on the installation

Preliminary, site-specific results. Results vary by site, system and operation. The client is not named.

The site

A cooling system, measured on its own meters.

Phase 1 cooling at a Hong Kong data centre: two cooling towers and three chillers. Energy and water were read from the site's own meters, then compared with the same three months a year later.

We chose a like-for-like window on purpose. Comparing the same months removes most seasonal differences, and the weather adjustment below deals with the rest.

Site
Data centre, Hong Kong
System
Phase 1 cooling: two cooling towers, three chillers
Installed
GRANDER Circulation Revitalisation Devices on the cooling and chilled-water circuits
Period
July–September 2025 vs July–September 2026
Method
Site meters. Energy weather-adjusted with CDD18.
Circulation unit fitted on a closed circuit between the chiller and the cooling consumers

How it was measured

Baseline. Install. Compare.

The same three months, a year apart. Energy was adjusted for weather. Water was compared as metered.

  • Baseline

    July–September 2025 cooling energy and water use, read from the site's own meters.

  • Install

    Circulation Revitalisation Devices fitted on the cooling circuits by licensed contractors. No power, no dosing.

  • Compare

    July–September 2026, with energy adjusted for cooling degree days (CDD18, 18 °C base, Hong Kong Airport).

According to GRANDER, a sealed core revitalises the water flowing past it. A GRANDER unit is not a filter and removes nothing from the water.

Weather adjustment

Cooler weather was taken out of the energy figure.

A cooler summer means chillers work less, so a raw comparison would overstate the saving. We therefore adjusted energy for cooling degree days.

2026 had about 2.1% fewer cooling degree days (1,084.50 down to 1,061.80). Unadjusted energy was 15.93% lower. Of that raw reduction, about 9,269 kWh is accounted for by cooler weather. The weather-adjusted reduction is 61,288 kWh, about 14.1%. That is the figure we report.

From the raw reduction

70,557 kWh lower energy, before weather is taken out.

Weather-adjusted saving61,288 kWh
Accounted for by weather9,269 kWh
Raw reduction (unadjusted)70,557 kWh
Weather-adjusted savingAccounted for by cooler weather

The results

Before and after, side by side.

Energy, energy per cooling degree day, and water: July–September 2025 against the same months in 2026.

Weather-adjusted cooling energy fell about 14%. Water use fell about 28%.

Jul–Sep 2025Jul–Sep 2026

Energy consumption

kWh, Jul–Sep · unadjusted

−70,557 kWh · −15.93%

Energy consumption, July to September, unadjusted 2025: 442,815 kWh. 2026: 372,258 kWh. Unadjusted reduction 70,557 kWh, or 15.93%. 500400300 2001000 Thousand kWh 442,815 372,258 Jul–Sep2025 Jul–Sep2026

Energy per CDD18

kWh per cooling degree day · weather-normalised

−14.14%

Energy per CDD18, July to September, weather-normalised 2025: 408.31 kWh per CDD18. 2026: 350.59 kWh per CDD18. Reduction 14.14%. 500400300 2001000 kWh per CDD18 408.31 350.59 Jul–Sep2025 Jul–Sep2026

Water consumption

m³, Jul–Sep · unadjusted

−1,864 m³ · −27.87%

Water consumption, July to September, unadjusted 2025: 6,688 cubic metres. 2026: 4,824 cubic metres. Reduction 1,864 cubic metres, or 27.87%. 8,0006,0004,000 2,0000 m³ 6,688 4,824 Jul–Sep2025 Jul–Sep2026

Weather-adjusted energy reduction 61,288 kWh, about 14.1%. About 9,269 kWh of the raw 70,557 kWh reduction is explained by cooler weather. Water is an unadjusted comparison. CDD18 uses an 18 °C base at Hong Kong Airport. Preliminary, site-specific results.

Cost

Three months, then a year.

Electricity valued at HK$1.40/kWh on the weather-adjusted 61,288 kWh. Water valued at about HK$7.50/m³ on 1,864 m³. The annual figure is the three-month saving times four.

We show the rates so you can re-run the sums with your own tariffs.

HK$99,783.63 over three months. HK$399,134.50 a year, annualised.

ElectricityWater

Three-month and annualised utility savings, electricity and water Three months: electricity HK$85,803.63, water HK$13,980.00, combined HK$99,783.63. Annualised times four: electricity HK$343,214.50, water HK$55,920.00, combined HK$399,134.50. HK$400kHK$300k HK$200kHK$100k HK$0 Utility savings (HK$ thousands) HK$99,783.63 HK$399,134.50 HK$85,803.63 Water HK$13,980.00 HK$55,920.00 HK$343,214.50 Three months (Jul–Sep 2026 vs 2025) Annualised (× 4)

Annualised = three-month saving × 4, and assumes similar savings in every quarter. Preliminary, site-specific results.

The breakdown

ComponentThree monthsAnnualised (×4)
ElectricityHK$85,803.63HK$343,214.50
WaterHK$13,980.00HK$55,920.00
CombinedHK$99,783.63HK$399,134.50

Installation HK$1,916,000. Rates used for this study: HK$1.40/kWh and about HK$7.50/m³.

Payback

About 4.8 years, before recurring costs.

Cumulative savings at HK$399,134.50 a year, set against an indicative installation of HK$1,916,000. Simple payback, with no escalation or discounting.

This is a deliberately simple view. Your own figure depends on your tariffs, your system and how the plant is operated.

Indicative simple payback of 4.8 years.

Cumulative savingsInstallation HK$1,916,000

Indicative payback on HK$1,916,000 Cumulative savings of HK$399,134.50 a year reach the HK$1,916,000 installation cost at about 4.8 years. Figures at year one through six: HK$0.40 million, 0.80, 1.20, 1.60, 2.00 and 2.39 million. Indicative, before recurring costs. HK$2.5MHK$2.0M HK$1.5MHK$1.0M HK$0.5MHK$0 HK$ millions Investment HK$1,916,000 HK$0.40M HK$0.80M HK$1.20M HK$1.60M HK$2.39M Payback about 4.8 years indicative, before recurring costs 4.8 years 012 345 6 Years after installation

Simple payback = HK$1,916,000 ÷ HK$399,134.50 a year. Excludes recurring servicing and other costs, financing and taxes. Annual savings are annualised (×4) from one three-month period at one site. Preliminary and site-specific.

Carbon

About 98 tonnes of CO2 a year, annualised.

From the weather-adjusted energy saving, at 0.4 kg CO2e/kWh. The annual figure is the three-month saving times four.

About 24.5 tonnes over three months. About 98.1 tonnes a year, annualised.

CO2 avoided, case study, weather-adjusted About 24.5 tonnes of CO2 over three months, and about 98.1 tonnes a year annualised, at 0.4 kilograms of CO2e per kilowatt-hour on the weather-adjusted energy saving. 12510075 50250 Tonnes CO2 about 24.5 t about 98.1 t Three months(Jul–Sep) Annualised(× 4)

Weather-adjusted 61,288 kWh over Jul–Sep, annualised × 4 = about 245,150 kWh, at 0.4 kg CO2e/kWh. Preliminary, site-specific results.

Limits of this study

Preliminary, site-specific results.

This is one three-month comparison at one site, using a simple CDD18 weather model with no control for IT load or operating hours. Water is an unadjusted comparison. The annual figures multiply the three-month saving by four and assume similar savings in every quarter. Payback is indicative and excludes recurring servicing and other costs. Results vary by site, system and operation. The client is not named.

Measure it on your own site.

We start with one circuit, set a baseline on your meters and report the results before you commit further. Email us the site address and the system you would like to measure.

Book a site surveyEmail